Project Description
The PAR8 Data Centre facility consists of 4 No. buildings namely PAR8, 9, 10 & 11. Each building has an IT capacity of 19.2MW which will be deployed 3 floors of Data halls. The total site IT load is 76.8MW..
Our Input
Ethos provided full Mechanical & Electrical Design services right through to detailed design and the project is currently in construction. The facility has the following electrical and mechanical systems
Key Features
Electrical Systems
·3No separate utility Grid connections, utility provider(s) (Enedis/RTE)
.·MV/MV Transformers, consisting of 20/12.0kV, 20MVA Step-down/Isolation Transformers
·MV/LV Transformers, consisting of 12.0/0.42kV, 4MVA, Step-down Power Transformers
·2286kVA/1829kW Diesel Engine Generator plant consisting of 12.0kV rated alternators and remote (dry cooled) radiator system.
·Bulk Fuel storage and distribution system
·Power backbone infrastructure
·Earthing System, TN-C/TN-S
·Lightning Protection System
·UPS power distribution
·PMS Monitoring System
·Generator Control System and Site Switching System
·Fully Addressable Normal and Emergency Lighting and KNX Lighting Control System
·Security System, including CCTV, Access Control and Intruder Alarm
·Fire detection and protection, including Fire Suppression
·Leakage detection
·Structured cabling
Mechanical Systems
·Water Cooled Chillers
·CGM’s with chiller integration and Hybrid Dry Cooler integration
·CRAH Cooling
·Ventilation and Humidity Control Systems
·Forced Air Cooling
·Inergen Fire Suppression System
·Struxureware BMS
·Hybrid VRF system for Office Air Con
·Dedicated smoke extraction systems for Data Halls and Battery Rooms
·Water cooled air conditioning units for Battery Rooms
First Q Member(s)
Ethos Engineering
Services
MEP Design
- Building services design
Project Size
Approx 40,000m2
Date
Ongoing
Location
Dublin, Ireland