EdgeConnex Amsterdam

The NetherlandsData Centres

Project Description

This consists of 2 No. 10 MW COLO’s and associated electrical support rooms (Electrical Rooms, MDF Rooms, MV Rooms, etc).

Our Input

As part of the mechanical and electrical deliverables Ethos Engineering was commissioned to provide the design through BIM and Revit MEP was used for this project. The M&E services were developed to LOD 300 and transferred over to the main contractor to complete throughout the project. Ethos Engineering provided full electrical design services and Construction Administration support.

Key Features

The electrical support rooms are fully prefabricated pods that were manufactured off-site and positioned externally to the building to facilitate an accelerated construction programme.

The cooling was achieved by an all-air cooling system, utilising air side economisers (outside air) to cool the server spaces. The project also involved infrastructure extension and resilience, in relation to site MV supplies and connection to other telecoms infrastructure.

Worked closely with our Dutch First Q Partner – Smits van Burgst - to ensure local compliance, and offering a contact on the ground who was available to the client, while managing the entire design process from our Dublin Offices.

First Q Member(s)

Ethos Engineering

Services

MEP Design

  • Building services design

Project Size

20 MW

Date

Construction

Location

The Netherlands

Share